Zubair Field Oil Development Project

Zubair Field Oil Development Project

Directions

Project Information

Started 5/2013
Completed 2/2015

Project Description

Our teams in the Zubair oil field development Project Iraq-Basra working as a subcontractor for the DS and Sicim JV  successfully have completed in total of of 110,000 inch of spool fabrication and installation at their relevant locations at 52 well Hook ups and  5 degasation stations. our civil, coating team, painting team, Tie-in team and platform team have completed all related activities in the pipeline section and the piping section of the the project. main drive to those activities took an early start of all of welding 250 km of different size of flow lines and oil transfer lines of different sizes (6, 8, 10, 16, 24, 36 and 52 inch).

Our commissioning team still taking place at site until Jun of 2015